General Remarks
Compared to other energy efficient technologies,
such as Tunnel Kilns, the Third Generation VSBK is a low tech brick
kiln which can be built with locally available building materials
and operated with accurately working, but normal skilled labour.
However deficient construction quality can affect the production
flow and generate higher maintenance costs.
Investment Capital
For establishing a brickyard from the scratch,
costs of land and hardware (kiln, labour quarters and equipment)
determine the required capital investment. If no very advantageous
leasing contract can be made, land is the most important cost factor
for a new brick venture, especially in the peri-urban areas of Kabul.
A BTK covers an area of 3200-4000m2, while a
four-shaft VSBK requires only 400-500m2 land. With the actual land
price in the per-urban area of Kabul (60USD/m2), a VSBK requires
about 180’000USD or 8 million Afghani less investment capital for
land (3000m2 x 60USD/m2), than a BTK, only considering the land
for the kiln without counting the usually leased moulding and mining
area.
The land related cost savings of a VSBK brickyard
are partly absorbed by the higher kiln costs (about 40-70.000 USD
higher, depending on the site characteristics and the degree of
mechanisation selected).
As for every new venture, additional capital
(approximately the 40’000 USD) must be kept available for the initial
operation tuning and for optimising the production process, so that
the business can become profitable.
However, the actual investment costs are different
for each site and each production set-up and have to be calculated
carefully before comparing them with other options.
Rough calculations show that in areas where land
costs about 20 USD/m2, establishing a VSBK or a BTK venture requires
the same amount of approximately 120.000USD or 5.4 million Afghani,
(land for the kiln included, but without initial operation costs).
With increasing land prices, VSBK becomes the more economic solutions,
whereas in cheaper areas, establishing a BTK brickyard may be less
capital intensive than a VSBK.
Site Selection
A VSBK with 3-4 shafts can be established on
roughly one-sixth of the area needed by an equivalent BTK. However,
for soil mining and green brick production, that land area required
is no different to a BTK. A VSBK can be built either in flat or
sloping terrain. Sloping terrain offers more benefits during operation
because it eases the green brick transportation to the VSBK platform.
Some important factors to be considered while selecting site for
a VSBK includes the availability of raw materials (clay), access
to road and electricity (for mechanized VSBK), availability of water
and country specific legal compliances. Soil selection forms an
integral part of VSBK site selection. VSBK requires good soil quality
to cope with its rapid firing system.
Building Material
Except fire resisting refractory bricks for shaft
construction, VSBK can be built with commonly available building
materials such as normal brick, sand, cement, aggregates and iron
bars. Some metal parts such as I beam and C channels are used to
support unloading system and shaft wall. Fired clay dust is used
as insulation material. Screw jack or hydraulic systems are the
only mechanized devices required for operation, along with some
iron bars.
Construction Management and Supervision and required
Skills of the Construction Labour
A well planned and managed VSBK construction
site can be completed within 80 days. Timely availability of building
materials and an adequate number of masons and labourers are essential
to complete a VSBK within the planned time period. Equally, the
quality of building materials is important, especially for foundation
work and shaft construction. Use of second-hand or low grade materials
may reduce up front investment but it will increase the maintenance
cost and also creates operational problems. It is advised to construct
a VSBK under the supervision of experience engineer/overseer and
with well trained masons and labourers. A well built VSBK will have
a life span of at least 15 years.
Critical Elements
The most critical element in VSBK construction
is the shaft. It requires special skills with refractory masonry,
since only +/- 2mm tolerance is allowed in shaft construction. Hence
it requires refractory bricks with uniform shape and size and masons
with specialised skills.
The foundation is another critical element. A
VSBK with two shafts weighs about 1000 t, including weight of green
bricks on top of its platform. Hence strong foundation has to be
laid to withstand this load and the horizontal movement during earth
quakes. It is always advisable to consult a structural engineers
in case of poor sub soil condition.
|